Bridges, buildings, roads and irrigation works delivered across Nepal since 2045 B.S.
| S.N. | Name of Project | Name of Client | Agreement Date | Completion Date | Total Contract Amount, NRs. (Including VAT) | Total Final Received Amount, NRs. (Including VAT) |
|---|---|---|---|---|---|---|
| 1 | Contract No. LRBP – 184/2014, Construction of Bridge construction work of Khani Khola and Khaire Khola Bridges, Ramechhap along Manthali – Galpa – Chauri Road in Ramechhap District | LOCAL ROAD BRIDGE PROGRAMME (LRBP), Manbhawan, Lalitpur | 10 May 2010 | 28 Feb 2018 | 3,82,56,559.00 | 3,39,39,385.16 |
| 2 | Construction of Kajalakhola Steel Girder RCC Deck Bridge | Sunsari Morang Bridge Construction Project, Itahari, Sunsari | 10 Poush 2071 B.S. | 2,84,45,094.44 | 2,84,45,094.44 | |
| 3 | 3 Steel Truss Bridge with RCC Decking over Singati Khola and Tamakoshi River,Contract no. UTKHEP/13-206306430/2064/66 | Upper Tamakoshi Hydropower Limited, Kathmandu. | 6 Jul 2007 | 21 Feb 2013 | 11,00,84,550.73 | 11,00,84,550.73 |
| 4 | Construction of RCC Bridge Over Bakraha Khola Brdge at Morang District, Contract No.SMBCP – 07/066/067 | DOR, Hulaki Rajmarg Project, Project Office, Itahari, Sunsari | 25 Asar 2067 B.S. | 21 Falgun 2071 B.S. | 6,76,00,779.46 | 6,76,00,779.46 |
| 5 | Construction of RCC Arch Bridge over Manohara River | Division Road Office,Lalitpur | 23 Asar 2067 B.S. | 28 Ashwin 2071 B.S. | 3,69,32,986.88 | 3,69,44,060.89 |
| 6 | Construction of RCC Bridge over Bagmati River, Bagmati Manohara Dovan Shankhamul, Contract No. 161/066/067 | DOR, CRRD, DRO Kathmandu | 27 Asar 2067 B.S. | 27 Poush 2069 B.S. | 4,17,34,275.17 | 1,80,90,022.61 |
| 7 | Construction of Motorable Steel Truss Bridge over Marsyandi River at Tarkughat in Tanahun/Lamung | Division Road Office,Tanahun | 12 Asar 2064 B.S. | 9 Jestha 2067 B.S. | 8,09,52,729.92 | 8,08,81,863.10 |
| 8 | Construction of Manusmara Brdige at Hardi – Malangawa – Bagmati Road, Chhartauna, Sarlahi, Contract No.: 51/066/067 | DOR, Hulaki Rajmarg Project, Project Office, Janakpur. | 32 Asar 2067 B.S. | 3,12,59,417.36 | 2,70,94,673.35 | |
| 9 | Construction of RCC T – Beam Bridge Over Bhaluhi River at Maheshpur – Trivenidham Road, Contract No.48/063/064 | Western Division Road Office No.4, Butwal | 10 Jul 2007 | 26 Jun 2011 | 4,05,27,753.97 | 4,65,50,199.32 |
| 10 | Constrution of Molung khola Suspension Bridge 257.8m in Tunkey basis Package, Contract No. CTP10 – 067/068 | DoLIDaAR, suspension Bridge Division Shreemahal, Pulchwok, Lalitpur. | 2 Asar 2068 B.S. | 30 Shrawan 2071 B.S. | 99,15,750.00 | 99,15,750.00 |
| 11 | Repair & Maintenance works of Different Bridges at Prithvi & Siddharth Highway and Feeder Roads under Contract No. BBPCU – BMM- 337320 – 072/073 -05 | DRO, Bridge Project Mid Regiona Sector No., Chakupat, Lalitpur. | 24 Chaitra 2072 B.S. | 24 Chaitra 2073 B.S. | 1,23,55,210.94 | 11,91,94,310.94 |
| 12 | Repair & Maintenance works of Different Bridges MRM & TRP under Contract No. BBPCU – BMM- 337320 – 072/073 -04 | DRO, Bridge Project Mid Regiona Sector No., Chakupat, Lalitpur. | 24 Chaitra 2072 B.S. | 24 Chaitra 2073 B.S. | 10,81,96,423.00 | 10,26,63,516.59 |
| 13 | Repair & Maintenance works of different Bridges along Manahendra Highway, Contract No.BBPCU – BMM- 337320 – 072/073 – 43 | DRO, Bridge Branch, Bridge Project, Mid Region Sector No. 02, New Baneshwor, Kathnandu. | 12 Ashwin 2073 B.S. | 2 Jestha 2074 B.S. | 5,56,88,078.06 | 4,73,21,989.94 |
| 14 | Repair & Maintenance works of different BridgesContract No.BBPCU – BMM- 337320 – 072/073 – 001 | DRO, Bridge Branch, Bridge Project, Mid Region Sector No. 02, New Baneshwor, Kathnandu. | 24 Chaitra 2072 B.S. | 24 Chaitra 2073 B.S. | 7,87,52,682.64 | 7,42,09,782.33 |
| 15 | Repair & Maintenance works of different Bridges of Highway and Feeder Roads Contract No.BBPCU – BMM- 337320 – 072/073 – 05 | DRO, Bridge Project, Mid Region Sector No. 02, New Baneshwor, Kathnandu. | 24 Chaitra 2072 B.S. | 24 Chaitra 2073 B.S. | 12,35,52,109.14 | 11,91,94,310.94 |
| 16 | Repair & Maintenance works of different Bridges of Highway and Feeder Roads Contract No.BBPCU – BMM- 337320 – 072/073 – 04 | DRO, Bridge Project, Mid Region Sector No. 02, New Baneshwor, Kathnandu. | 24 Chaitra 2072 B.S. | 24 Chaitra 2073 B.S. | 10,81,96,423.00 | 10,26,63,516.59 |
| 17 | Repair & Maintenance works of Bgmati River Bridges (Old ), Thapathali and Dhovikhola Bridges, Anamnagar, Kathmandu, Contract No.PCU – BM- CR – 071/072 – 29 | DRO, Bridge Project, Mid Region Sector No. 02, New Baneshwor, Kathnandu. | 28 Asar 2072 B.S. | 23 Bhadra 2073 B.S. | 2,26,66,596.00 | 2,58,63,447.00 |
| 18 | Maintenance & Repair works of Manahara River Bridge at Kailali, along East – West Highway, Contract No. PCU – BM- WR – 071/072 – 210 | DRO, Bridge Branch, Bridge Project Western Area, Sector No. 03 Nepalgunj, Banke. | 11 Jestha 2072 B.S. | 20 Asar 2072 B.S. | 40,66,425.09 | 40,66,425.09 |
| 19 | Maintenance & Repair works of Various Bridges, Contract No. BB – PCU – BMM – 337320 – 072/073 – 008 | DRO, Bridge Branch, Bridge Project Western Area, Sector No. 03 Nepalgunj, Banke. | 24 Chaitra 2072 B.S. | 23 Chaitra 2073 B.S. | 6,93,13,589.47 | 6,87,13,568.47 |
| 20 | Repair & Maintenance works of Bagmati River Bridge (Old), Thapathali and Dhobikhola Bridge, Anamnagar, Kathmandu, Contract No. PCU – BM- CR – 071/072 – 29 | DRO, Bridge Project Mid Regiona Sector No., Chakupat, Lalitpur. | 28 Asar 2072 B.S. | 23 Bhadra 2073 B.S. | 2,26,66,596.00 | 2,58,63,447.00 |
| 21 | Repair & Maintenance works of Bagmati River Bridge (Old), Thapathali and Dhobikhola Bridges: Godawari – Lalitpur, Dhokaphedi – Bhaise Bhimphedi, Nandemata Kavrel, Chokinchilla – Bhaktapur, Hanumante – Bhaktapur, Lothar, Makawanpur, Tuteshw – VI), Contract No. PCU – BM- MR – 071/072 – 6 | DRO, Bridge Project Mid Regiona Sector No., Chakupat, Lalitpur. | 2 Jestha 2072 B.S. | 10 Jestha 2073 B.S. | 4,76,53,275.37 | 3,07,72,529.65 |
| 22 | Repair & Maintenance works of Kankai & Solti Bridges, Contract No. PCU – BM- ER – 071/072/04 | DRO, Bridge Project Mid Regiona Sector No., Chakupat, Lalitpur. | 6 Jestha 2072 B.S. | 3 Chaitra 2072 B.S. | 2,22,86,380.21 | 2,30,54,316.62 |
| 23 | Repair & Maintenance works of Bagmati & Chandhi Bridge, Contract No. PCU – BM- ER – 071/072/03 | DRO, Bridge Project Mid Regiona Sector No., Chakupat, Lalitpur. | 6 Jestha 2072 B.S. | 3 Chaitra 2072 B.S. | 2,38,19,214.04 | 2,23,50,150.00 |
| 24 | Repair & Maintenance works of Bagmati & Chandhi Bridge, Contract No. PCU – BM- ER – 071/072/03 | DRO, Bridge Project Mid Regiona Sector No., Chakupat, Lalitpur. | 6 Jestha 2072 B.S. | 3 Chaitra 2072 B.S. | 2,38,19,214.04 | 2,23,50,150.00 |
| 25 | Repairing and Maintenance Different Bridges: Bagmati & Dhobikhola, Kathmandu, Betrawati, Nuwakot, chakukhola, sindhupalchwok, 1no. & 2 Amlekhgunj, Ek No Pathlaiya, Unashi & Bangadhi Bara (Package – II), Contract No: BP/BM/069/070 – 07 | Bridge Project Mid Region Sector New Baneshwor, Kathmandu. | 20 Asar 2070 B.S. | 9 19 2071 B.S. | 6,50,80,935.81 | 6,50,54,317.40 |
| 26 | Repair & Maintenance works of Tamor & Maikhola Bridges under Contract No. BP – BM – 2069/2070 – 1 | Bridge Project, Babarmahal, Kathmandu. | 2 Asar 2069 B.S. | 20 Jestha 2071 B.S. | 9,20,30,453.95 | 9,20,30,453.95 |
| 27 | Repair & Maintenance works of Marsyangdi Bridge, Kaligandaki Bridge & Bheri Bridge, Contract No. BP – M – 660/067 – 068, 02,05 & 06 | Bridge Project, Babarmahal, Kathmandu. | 8 Baisakh 2068 B.S. | 30 Chaitra 2068 B.S. | 7,41,82,259.65 | 7,41,82,259.65 |
| 28 | Repair & Maintenance works of Mugling Bridge at Trishuli River in Prithivi Highway | Bridge Project, Babarmahal, Kathmandu. | 6 Baisakh 2068 B.S. | 30 Chaitra 2068 B.S. | 4,23,73,868.43 | 4,49,72,906.94 |